Service | Pipe Freezing |
---|---|
Client / Work Location | Hong Kong International Airport |
Date: | Oct, 2022 |
Size | DN80 (3") |
Medium | Chilled Water |
Operating Pressure | 4 Bar |
Operating Temperature | 7°C |
Problem | Client wants to blank off the old pipes |
Solution | Perform pipe freezing to isolate the water, avoid draining off water from the whole system and kept the other parts of system running. |